Schedule
The Innovate Mound project will rebuild one of the most important corridors in Southeast Michigan. Below is the anticipated project schedule.
2022
Miscellaneous Storm Sewer and Sanitary Sewer Improvements Mound Road from 15 Mile Road to M Miscellaneous Water -59 Improvements Mound Road from 15 Mile Road to M-59
Q1
Open to Traffic (Excludes periodic short term lane closures) Mound Road will have all lanes open to traffic, and construction will be suspended until March 2022, except for utility work utilizing short term lane closures
Q2-Q4
Phase 1 Construction Construction on Mound Road from 15 Mile Road to M-59 is anticipated to start in March 2022 and end in Nov ember 2022
2023
Q1
Open to Traffic (Excludes periodic short term lane closures) Mound Road will have all lanes open to traffic, and construction will be suspended until April 2023, except for utility work utilizing short term lane closures
Q2-Q4
Phase 2 Construction Construction on Mound Road from 15 Mile Road to I-696 is anticipated to start in March 2023 and end in Nov ember 2023
2024
Construction Anticipated to Conclude