Innovate Mound Newsletter – April 2021
Located in the cities of Warren and Sterling Heights, Macomb County, Innovate Mound will reconstruct Mound Road between 11 Mile and M-59. Please share this information with your network and contact us with any thoughts, ideas, questions, or concerns.
With construction of the Innovate Mound project scheduled to begin later this summer, now is the time to subscribe to the Innovate Mound newsletter, follow us on social media, and invite your family, friends, and community to do the same.
Construction updates, lane closures and other critical information will be shared via these channels. To stay up-to-date with what’s going on with the reconstruction of Mound Road…subscribe, follow and invite!
The Innovate Mound project timeline for the first half of 2021 is as follows:
- Complete Design (In progress)
- Choose Contractor and Ombudsman (Late Spring 2021)
- Finalize Construction Details (Late Spring 2021)
- Start Construction (Summer 2021)
Completing the DesignOne of the most important parts of a project such as this is the design phase – a phase that significant efforts have been put toward thus far.“Right now, we’ve completed about 30 percent of the new road design,” said Bryan Santo, director of Macomb County Department of Roads. “We’ve done this with input from many residents, businesses, and others who have shared their thoughts and ideas with us.”The Innovate Mound project is slated to be complete in 2024. Read more about what’s coming up next with the Innovate Mound project on our website…
COMING UP NEXT ON THE PROJECT
Frequently Asked Questions
Do you have a question about the Innovate Mound project that you’d like to ask ? Email us today.
Q: When will construction on Mound Road start and be completed?
A: Construction is anticipated to commence in 2021. The estimated completion date is 2024.
For more information on the Innovate Mound project timeline, visit the timeline page on our website, or review the schedule below.
NOTE: The construction schedule is subject to change. Subscribe to our newsletter, or follow us on Facebook and Twitter to stay up-to-date on construction schedule updates as they arise.
2021
Segment 1 Construction
Dobry Drive to approximately 18 Mile Road
Duration: Summer 2021 to December 2021
Intersections
19 Mile Road, 18 1/2 Mile Road, 18 Mile Road
Bridge Work
Northbound Mound Road over Plum Brook
Southbound Mound Road over Plum Brook
2022
Segment 2 Construction
Approximately 18 Mile Road to approximately 14 Mile Road
Duration: March to November 2022
Intersections
17 Mile Road, 16 Mile Road, 15 Mile Road, 14 Mile Road
Bridge Work
Mound over Sterling Relief Drain
Mound over Big Beaver Creek
2023
Segment 3 Construction
Approximately 14 Mile Road to North of 11 Mile Road
Duration: March to November 2023
Intersections
Chicago Road
13 Mile Road
12 Mile Road
Bridge Work
Mound over Red Run Drain
Mound over Bear Creek
Construction schedule subject to change.