Innovate Mound Newsletter – July-August 2021
Located in the cities of Warren and Sterling Heights, Macomb County, Innovate Mound will reconstruct Mound Road between 11 Mile and M-59. Please share this information with your network and contact us with any thoughts, ideas, questions, or concerns.
Learn More About Mound Road Construction
The transformational $217 million Innovate Mound project to rebuild Mound Road from 11 Mile Road to M-59 is breaking ground this month. Get the latest project information and construction details in-person. Join us for:
Innovate Mound 301
A community open house where the project team and contractor will share what to expect as construction kicks off this month and continues through 2023. Team members will be available to answer questions regarding construction and the schedule.
Bring Your Family and Neighbors
This is a family-friendly event! Enjoy outdoor activities and ice cream while learning about the event location host, Chardam Gear Company.
Thursday, August 26, 2021
4 p.m. to 7 p.m.
Presentations at 4:15 p.m., 5:15 p.m., and 6:15 p.m.
Chardam Gear Company
40805 Mound Road
Sterling Heights, MI 48301
We look forward to seeing you there!
For more information: Visit InnovateMound.org Follow us at: facebook.com/innovatemound twitter.com/@innovatemound Call 1-855-Mound 4U (668-6348)
With advance notice of seven days, accommodations can be made for persons with disabilities and/or limited English-speaking ability and persons needing auxiliary aids or services of interpreters, signers, readers or large print. Please contact Kelly Sweeny at 313-648-1062
Meet the Innovate Mound Team: Steve Griffith and Ryan Sarmiento
Innovate Mound project team members from HNTB Steve Griffith, senior resident engineer, and Ryan Sarmiento, assistant resident engineer, provided an inside look at their work with the Macomb County Department of Roads on the project as it prepares to head into the construction phase later this summer.
Visit the Innovate Mound website to read what they had to say about their work on the Innovate Mound project.
“OPEN DURING CONSTRUCTION”
Flyer and Social Graphic
Available to Businesses
The Innovate Mound team has prepared an “Open For Business During Construction” flyer and social media graphics for local businesses to display at their brick-and-mortar location, as well as on their social media channels during the reconstruction of the Mound Road corridor to let the public know that they are open for business.
You can download the printable graphics on the Innovate Mound website.
Frequently Asked Questions
Do you have a question about the Innovate Mound project that you’d like to ask ? Email us today.
Q: When will actual construction on Mound Road start?
A: Construction is anticipated to commence in late August 2021. The estimated completion date is 2024.
For more information on the Innovate Mound project timeline, visit the timeline page on our website, or review the schedule below.
2021
- Temporary widening of Mound Road from Dobry Drive to 15 Mile Road in the median to prepare for the reconstruction starting in Spring of 2022
- Storm sewer and municipal utility work
- Temporary traffic signal work
- Widening of the Mound Road bridges over Plum Brook Creek
NOTE: The construction schedule is subject to change. Subscribe to our newsletter, or follow us on Facebook and Twitter to stay up-to-date on construction schedule updates as they arise.