Located in the cities of Warren and Sterling Heights, Macomb County, Innovate Mound will reconstruct Mound Road between 11 Mile Road and M-59. Please share this information with your network and contact us with any thoughts, ideas, questions, or concerns.
March-November 2022
Typical Work Zone Mound Road
From North of 15 Mile to M-59
Typical Work Zone March-August
![Cc47d05d F39b 7e01 9e30 D838fd40a585 Cc47d05d F39b 7e01 9e30 D838fd40a585](https://innovatemound.org/wp-content/uploads/2022/06/cc47d05d-f39b-7e01-9e30-d838fd40a585.jpeg)
On March 3, northbound and southbound Mound traffic was shifted with two lanes maintained in each direction on the left lane and temporary pavement to begin reconstruction of the outside lanes. Mound Road traffic will remain in this configuration until mid-August of 2022.
Typical Work Zone August – November
![Ec5a7a02 C1e3 225a Ae6d 6c678a87872a Ec5a7a02 C1e3 225a Ae6d 6c678a87872a](https://innovatemound.org/wp-content/uploads/2022/06/ec5a7a02-c1e3-225a-ae6d-6c678a87872a.jpeg)
In August, traffic will be shifted to the newly constructed outside lanes to allow for the reconstruction of the median lanes and crossovers.
![9b3103b6 A578 9b5a 378c Eb045e007089 9b3103b6 A578 9b5a 378c Eb045e007089](https://innovatemound.org/wp-content/uploads/2022/06/9b3103b6-a578-9b5a-378c-eb045e007089.png)
February Virtual Event Kicks Off 2022 Construction
Innovate Mound is the transformational project to rebuild Mound Road from I-696 to M-59. Segment 1 construction from 15 1/2 Mile Road to M-59 will take place March through November 2022.
Virtual Meetings were held on Thursday, February 17, 2022, and the public was given several opportunities to pick up project materials at locations throughout Macomb County. The 401 event allowed residents, commuters, and users of Mound Road to learn about the 2022 project schedule, construction plans, and offered an opportunity to ask questions.
Unable to attend?
If you missed the public event, you can visit the 401 event page on our site for videos, presentations, and graphics.
Innovate Mound 401 Presentation
![Come In Come In](https://innovatemound.org/wp-content/uploads/2022/06/come_in.jpeg)
“OPEN DURING CONSTRUCTION”
Flyer and Social Graphic Available to Businesses
Local businesses are encouraged to download the “Open For Business During Construction” flyer and social media graphics to display at their brick-and-mortar location, as well as on their social media channels during the reconstruction of the Mound Road corridor. These materials will help ensure the public knows your business is open for business during construction.